Prince William Street Project

Project update

October 11, 2018:  Prince William Street will be closed to through traffic from Grant Avenue to Wellington Road between 8 AM – 5PM Monday – Friday for utility and roadway work.

PrinceWilliam Street will be closed to through traffic from Grant Avenue to Wellington Road between 8 AM – 5PM Saturday, October 13, 2018 for utility and roadway work.

Water line
Our Public Works team met with the community at City Hall to discuss the Prince William Street project.  Staff presented information on the project and solicited feedback.  Links to this information are shared below.  All documents are in PDF format.
 

Project Status:

 

Underground Electric, Comcast and Verizon – completed

Columbia Gas work – completed

Advertised for construction – December 12, 2017

Bids received – February 9, 2018

Award Project – June 2018

Begin Construction – July 2018
Contractor - Fort Myer Construction and Utility Services Company

Project Complete – Spring 2019   


Informational Resources:


About the lights along Prince William Street (Sept. 17, 2018)
Construction Update to Citizens (Sept 5, 2018)
Pre-Construction Citizens Presentation (June 20, 2018)
Pre-construction Update to residents (letter June 8, 2018)
Prince William Street May 11th Meeting  (letter to residents)
Typical Section 36X24 one side sidewalk left
Typical Section 26X24
Prince William Street Aerial Outfall  (Note: very large PDF = 32MB)
Prince William Street Roadway Plan
Prince William Street Water and Sewer Plan
Prince William Street Aerial  (Note: very large PDF = 46 MB) 
Public Meeting Presentation Slideshow
Fact Sheet