The Dean DrivDean Drive Extensione Extended Project  (T-030) extends Dean Drive approximately 1,500 feet from the existing cul-de-sac, south of Nokesville Road, to the Animal Shelter driveway. 

  • The extended roadway section will have curbs, gutters, and sidewalks on both sides. Existing culverts will be extended and stormwater management will be included, and Foster Drive will be modified to include two T-intersections and realigned with Dean Drive.


Project Status:

  • On site survey and investigatory fieldwork: October 2018 – March 2019
  • Design to be completed: Winter 2019/2020
  • Begin construction: Spring 2020